Activity List    (42 records)       Sort By  
Case Number  Activity Date  Activity Type   
Case Name   
Summary   
15-1870-E-CN  10/29/2019  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Progress Report, filed by Counsel for Transource West Virginia, LLC (Closed Entry)

15-1870-E-CN  03/04/2019  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Final Order that Case No. 18-0085-E-C is dismissed with prejudice as resolved; etc. Case Final. Removing from open docket.

15-1870-E-CN  02/25/2019  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Final Progress Report, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  01/25/2019  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Status Report and Request for a brief additional period to finish the final steps of the settlement process, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  01/11/2019  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Progress Report, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  01/02/2019  Incoming Document  View PDF / Download
Transource West Virginia, LLC 

Transcript from hearing held on December 19, 2018 in Charleston, West Virginia before the Commission.

15-1870-E-CN  12/12/2018  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order that the evidentiary hearing in this case is set for 12/19/2018; etc. For details see Internet Hearing Information.

15-1870-E-CN  12/04/2018  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Pursuant to the 11/30/2018 Commission Procedural Order, copy of two maps, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  11/30/2018  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order that Transource West Virginia shall file, on or before 12/4/2018, a map as reasonably accurate as possible under the circumstances, showing the planned route as approved in Case No. 15-1870-E-CN, the current planned route, and the location of the Dalzell and Pokrandt properties clearly marked; that Transource should file a copy of the map shown in figure 3 of the 7/31/2018 Transource WV Report, with the locations of the Dalzell and Pokrandt properties clearly marked; that each party shall be prepared to make, at the beginning of the evidentiary hearing, an opening statement setting forth the factual and legal positions of that party; etc.

15-1870-E-CN  11/28/2018  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order that the Commission will not institute a prudence review in Case No. 15-1870-E-CN; that the Motion for Clarification filed by Mr. Dalzell has been addressed by this Order and is denied; etc.

15-1870-E-CN  11/01/2018  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order that Mr. Pokrandt's Motion to Compel is denied; that Mr. Pokrandt's request to add Appalachian Power Company as a defendant in this case is denied; that the Motion for Clarification filed by Mr. Pokrandt has been addressed by this Order; setting this matter for an evidentiary hearing on 12/5/2018; For details see Internet Hearing Information; requiring Transource WV to come to the hearing prepared to explain why the currently planned route of the transmission line across the Pokrandt and Dazell properties is necessary and does not constitute a change of scope for the Project certificated in Case No. 15-1870-E-CN; etc.

15-1870-E-CN  08/22/2018  Process   
Transource West Virginia, LLC 

To Commission for Assignment Conference

15-1870-E-CN  07/31/2018  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Report mandated by the 7/17/2018 Commission Order, filed by Counsel for Transource

15-1870-E-CN  07/17/2018  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order reopening Case No. 15-1870-E-CN for the limited purpose of reviewing whether there has been sufficient change in the scope of the project and whether the notice provided was sufficient; that Transource West Virginia, LLC file, within two weeks, a report including various information; that Case No. 18-1017-E-C is dismissed and the Complainant is joined in Case No. 18-0085-E-C; granting interim relief in part in that Case No. 15-1870-E-CN is reopened; dismissing Case No. 18-0388-E-C; etc.Case remains closed pending further Commission order.

15-1870-E-CN  01/06/2017  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Order Granting Approval, filed by Counsel for Transource West Virginia, LLC (Closed Entry)

15-1870-E-CN  07/07/2016  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order that, without approving the underlying terms and conditions of the agreement, the Commission grants its consent and approval for Transource West Virginia to enter into the Agreement that was attached to the Joint Stipulation filed on 5/5/2016; that in all other respects, the 6/29/2016 Commission Order remains in full force and effect; etc. (closed entry)

15-1870-E-CN  06/29/2016  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Final Order granting the application for a Certificate of Public Convenience and Necessity filed on 11/19/2015, is modified by the Joint Stipulation and Agreement for Settlement; that the Joint Stipulation and Agreement for Settlement filed on 5/5/2016, Attachment A, as adopted as a reasonable resolution of this case; directing Transource West Virginia to file a letter informing the Commission of substantial completion of the proposed Project, as a closed entry in this case; etc. Case Final. Removing from open docket.

15-1870-E-CN  06/22/2016  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Affidavits of publication, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  06/16/2016  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Proposed Order, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  05/18/2016  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Pursuant to the 05/17/2016 Commission Procedural Order, map illustrating the location of the Modified Project, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  05/17/2016  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order directing Transource West Virginia to publish a copy of the attached Notice of Modified Project with Facilities to be Constructed in Kanawha and Roane Counties in each of the Cities of Beckley, Bluefield, Charleston, Clarksburg, Elkins, Fairmont, Huntington, Keyser, Lewisburg, Logan, Martinsburg, Morgantown, Moundsville, Parkersburg, Point Pleasant, Weirton, Welch, Wheeling, and Williamson, and to file all Affidavits of Publication immediately upon receipt; directing Transource to file a map illustrating the locations of the Modified Project; etc.

15-1870-E-CN  05/13/2016  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Proposed publication order; Revised Exhibit 2; and Request for the Commission to issue an order, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  05/05/2016  Incoming Document  View PDF / Text / Download
Transource West Virginia, LLC 

Joint stipulation and Agreement, filed by Counsel for Transource West Virginia, LLC

15-1870-E-CN  04/22/2016  Order  View PDF / Text / Download
Transource West Virginia, LLC 

Commission Procedural Order that on or before 4:00 p.m., 5/6/2016, the parties shall file a joint status update; etc.

15-1870-E-CN  04/07/2016  Memo  View PDF / Text / Download
Transource West Virginia, LLC 

Further Staff Memo filed by: Auville, John

First Prev of 2 Next Last